Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 26, 2020 Pdfprep2020-10-26T22:31:34+00:00 The following is a network diagram for a project. What is the critical path for the project?A . A-B-D-GB . A-B-E-GC . A-C-F-GD . A-C-E-G View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.