Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 29, 2020 Pdfprep2020-11-29T11:38:50+00:00 The following is a network diagram for a project. What is the critical path for the project?A . A-B-C-F-G-IB . A-B-C-F-H-IC . A-D-E-F-G-ID . A-D-E-F-H-I View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.