What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
A .  $50
B .  $100
C .  $125
D .  $175

Answer: C

Leave a Reply

Your email address will not be published.