What is the first thing that a team should do to estimate user stories for a project?

Posted by: Pdfprep Category: PMI-200 Tags: , ,

What is the first thing that a team should do to estimate user stories for a project?
A . Sort the user stories according to priority.
B . Schedule a team meeting to understand them.
C . Define the story points measure.
D . Estimate through function point analysis.

Answer: C