What is the goal of the ‘identify context’ step as part of the risk management procedure?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

What is the goal of the ‘identify context’ step as part of the risk management procedure?
A . Identify responses to risks identified in the Business Case
B . Gather information about the project environment and objectives
C . Gather information about risks for inclusion in Highlight Reports to the Project Board
D . Identify the threats and opportunities that may affect the project’s objectives

Answer: B