Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 30, 2020 Pdfprep2020-11-30T13:37:31+00:00 What is the number of stakeholders, if the project has 28 potential communication channels?A . 7B . 8C . 14D . 16 View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.