What is the third interest?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

User and Supplier are two of the three primary stakeholder interests that must be represented on the Project Board at all times.

What is the third interest?
A . Customer
B . Business
C . Programme
D . Corporate

Answer: B