PdfPrep.com

What must the BA do to ensure maximum benefit for the stakeholders?

A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity.

What must the BA do to ensure maximum benefit for the stakeholders?
A . Ensure users are trained based on requirements
B . Apply quality control on requirements
C . Utilize requirements documentation template
D . Maintain requirements based on priority

Answer: D

Exit mobile version