Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: December 2, 2020 Pdfprep2020-12-02T20:22:27+00:00 What type of progress control is a Checkpoint Report?A . Event-drivenB . Exception-basedC . Time-drivenD . Ad hoc-based View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.