When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
A .  Negative
B .  Zero
C .  Positive
D .  Free

Answer: C