When considering risks, which describes an opportunity in a project?

Posted by: Pdfprep Category: PRF Tags: , ,

When considering risks, which describes an opportunity in a project?
A .  An uncertain event that could have a negative impact on objectives
B .  An uncertain event that could have a favourable impact on objectives
C .  An event that has occurred resulting in a negative impact on objectives
D .  An event that has occurred resulting in a favourable impact on objectives

Answer: B