When does the project team determine which dependencies are discretionary?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

When does the project team determine which dependencies are discretionary?
A .  Before the Define Activities process
B .  During the Define Activities process
C .  Before the Sequence Activities process
D .  During the Sequence Activities process

Answer: D