When each link in the supply chain builds in extra safety in the planned requirements creates what?

When each link in the supply chain builds in extra safety in the planned requirements creates what?
A . Higher Quality
B . Reduced Inventory
C . Higher Customer Satisfaction
D . Bullwhip effect

Answer: D

Explanation:

When each link in the supply chain builds in extra safety in the planned requirements creates the bullwhip effect. Synchronization across the supply chain is the only way to resolve this bullwhip effect.