When is the Risk Management Strategy produced?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

When is the Risk Management Strategy produced?
A . After authorization has been given to proceed with the initiation stage
B . Before the planning of the initiation stage
C . As soon as the Project Manager has been appointed at start-up
D . After the Project Board have approved the Project Initiation Documentation

Answer: A