When it is forecast that one or more tolerances are to be exceeded, what should happen first?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

When it is forecast that one or more tolerances are to be exceeded, what should happen first?
A . The next higher level of management will begin to execute management by exception
B . The appropriate level of management must refer the matter to the next higher level
C . The Project Plan will be replaced by a fallback plan
D . The appropriate level of management will automatically produce and execute an Exception Plan to recover from the deviation without referral

Answer: B