Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?
A . Review the stage status
B . Review work package status
C . Report Highlights
D . Take corrective action

Answer: C