Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
A .  Update
B .  Preventive action
C .  Defect repair
D .  Corrective action

Answer: D