Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
A .  Information management systems
B .  Work performance reports
C .  Stakeholder analysis
D .  Data gathering and representation

Answer: A