Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
A .  Cost variance (CV)
B .  Cost performance index (CPI)
C .  Budget at completion (BAC)
D .  Variance at completion (VAC)

Answer: B

Leave a Reply

Your email address will not be published.