Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A .  Project team
B .  Focus group
C .  Change control board
D .  Project stakeholders

Answer: C