Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
A .  Work performance data
B .  Project documents
C .  Scope baseline
D .  Requirements documentation

Answer: B