PdfPrep.com

Which is NOT an objective of the Controlling a Stage process?

Which is NOT an objective of the Controlling a Stage process?
A .  Implement actions to control the impact of risks that occur during the stage
B .  Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
C .  Update the Business Case with any changes agreed with the Project Board
D .  Coordinate the delivery of products as agreed in the Stage Plan

Answer: C

Exit mobile version