Which items are an output of the Perform Integrated Change Control process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which items are an output of the Perform Integrated Change Control process?
A .  Work performance reports
B .  Accepted deliverables
C .  Project management plan updates
D .  Organizational process assets

Answer: C