Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?
A . Project Manager
B . Project Board
C . Team Manager
D . Corporate or programme management

Answer: B