Which of the following describes risk proximity?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which of the following describes risk proximity?
A . The timeframe over which the risk mitigation actions should be implemented
B . The schedule for the risk management activities related to a plan
C . The timeframe over which a risk will be monitored by the risk owner
D . The timeframe for when the risk might materialize

Answer: D