PdfPrep.com

Which of the following is a valid constraint?

A business analyst (BA) is defining constraints for a project.

Which of the following is a valid constraint?
A . “The solution must be implemented in six (6) months.”
B . “The solution must increase sales by 20%.”
C . “The solution must promote workplace safety.”
D . “The solution must reduce support calls by 20%.”

Answer: B