Which of the following is FALSE?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which of the following is FALSE?
A . Manage risks is a PRINCE2 principle
B . Manage by exception is a PRINCE2 principle
C . Focus on products is a PRINCE2 principle
D . Tailor to suit the project environment is a PRINCE2 principle

Answer: A