Posted by: Pdfprep Category: CSM-001 Tags: CSM-001 exam questions, CSM-001 practice exam, GAQM certification Post Date: November 16, 2020 Pdfprep2020-11-16T13:39:06+00:00 Which of the following is not reflected in a Sprint Burndown Chart?A . Total Days in SprintB . Number of Tasks RemainingC . Day of SprintD . Work Hours Remaining View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.