Which of the following is the Business Case used for during the Managing a Stage Boundary process?

Posted by: Pdfprep Category: PRF Tags: , ,

Which of the following is the Business Case used for during the Managing a Stage Boundary process?
A .  Enable the Project Board to decide whether or not to authorize the project
B .  Justify the continuing viability of the project
C .  Enable the Project Board to decide whether or not to authorize project closure
D .  Justify the initiation of a project

Answer: B