Which of the following is TRUE about most project life cycles?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which of the following is TRUE about most project life cycles?
A .  Staffing level is highest at the start.
B .  The stakeholders’ influence is highest at the start.
C .  The level of uncertainty is lowest at the start.
D .  The cost of changes is highest at the start.

Answer: B