Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?

Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?
A . Exception Plan
B . Exception Report
C . Off-specification
D . Lessons Report

Answer: B