Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]

Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]
A . The total number of tests planned
B . The total number of requirements to be tested
C . The failure rate in testing already completed
D . The number of testers used for test execution so far

Answer: C