Which of the following planning systems would the demand forecast typically be fed into first?

Posted by: Pdfprep Category: CSCP Tags: , ,

Which of the following planning systems would the demand forecast typically be fed into first?
A .  DRP
B .  MPS
C .  MRP
D .  CRP
E .  business plan

Answer: A