PdfPrep.com

Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?

Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?
A . Lessons learned
B . Supporting details
C . Program management plan updates
D . Assumptions

Answer: A

Exit mobile version