Which of the following roles is MOST involved in checking the quality of the deliverables and supporting the project manager during the project?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Which of the following roles is MOST involved in checking the quality of the deliverables and supporting the project manager during the project?
A . Sponsor
B . Team leader
C . Project coordinator
D . Tester

Answer: D