Which of the following schemes would you use in selecting the audit team to optimize continuity, direction, availability, and technology transfer?

Posted by: Pdfprep Category: CQE Tags: , ,

You are requested by top management to establish an audit program of the quality systems in each branch plant of your firm.

Which of the following schemes would you use in selecting the audit team to optimize continuity, direction, availability, and technology transfer?
A . A full time audit staff.
B . All volunteer audit staff.
C . Hybrid audit staff (a proportion of answers a and b above).
D . An outside consulting firm.

Answer: C