Which of the following should the project manager tell the stakeholders?

In the review of a project status report, the slack is negative.

Which of the following should the project manager tell the stakeholders?
A . The project is behind schedule
B . The project is over budget
C . The project has float available
D . The project needs a gate review

Answer: A