Which of the following shows the correct sequence of planning tasks?

Posted by: Pdfprep Category: H13-621-ENU Tags: , ,

Which of the following shows the correct sequence of planning tasks?

A = Determine DR strategy.

B = Determine the need for Virtualization.

C = inventory of current situation.

D = Calculate capacity requirements.

E = Determine the backup strategy.

F = Estimate future growth.
A . B-D-C-F-E-A
B . C-D-B-A-F-E
C . C-D-F-B-A-E
D . A-B-E-C-D-F

Answer: C