Which of the following statements about the Closing a Project process are true?

Posted by: Pdfprep Category: PRF Tags: , ,

Which of the following statements about the Closing a Project process are true?

The Closing a Project process provides a fixed point for the receipt of completed Work

The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
A .  Only 1 is true
B .  Only 2 is true
C .  Both 1 and 2 are true
D .  Neither 1 or 2 are true

Answer: B