PdfPrep.com

Which of the following steps can the project manager take to make the meetings more productive?

Team members have reported that meetings are poorly attended and unproductive.

Which of the following steps can the project manager take to make the meetings more productive?
A . Discontinue the meetings with the poorest attendance.
B . Decrease the length of the meetings.
C . Distribute an agenda before each meeting.
D . Document team member attendance and report it to management.

Answer: C

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326

Exit mobile version