PdfPrep.com

Which of the following steps would involve the actioning of any planned risk responses and monitoring their effectiveness?

Which of the following steps would involve the actioning of any planned risk responses and monitoring their effectiveness?
A . Identify
B . Assess
C . Implement
D . Identify

Answer: C