Which of the following would be used to communicate a high level description of a major change that involved significant cost and risk to the organization?

Posted by: Pdfprep Category: ITIL-F Tags: , ,

Which of the following would be used to communicate a high level description of a major change that involved significant cost and risk to the organization?
A . Change proposal
B . Change policy
C . Service request
D . Risk register

Answer: A