PdfPrep.com

Which of the following would MOST likely require a risk practitioner to update the risk register?

Which of the following would MOST likely require a risk practitioner to update the risk register?
A . An alert being reported by the security operations center.
B . Development of a project schedule for implementing a risk response.
C . Engagement of a third party to conduct a vulnerability scan.
D . Completion of a project for implementing a new control.

Answer: D

Exit mobile version