Which one of the following does PRINCE2 also state for this principle?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

The PRINCE2 principle ‘continued business justification’ states that a requirement for a project is that… There is justifiable reason to start the project and justification should remain valid throughout the life of the project.

Which one of the following does PRINCE2 also state for this principle?
A . The Business Case will include details of all project risks
B . A product must deliver tangible, financial benefits
C . Clear ownership of the Business Case is documented
D . The justification is documented and approved

Answer: D