Which option describes something that should be provided by the project, but currently is not (or is forecast not to be) provided?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which option describes something that should be provided by the project, but currently is not (or is forecast not to be) provided?
A . Problem/concern
B . Concession
C . Off-specification
D . Exception Report

Answer: C