Which PRINCE2 role has a specific responsibility for advising on the selection of the development strategy, design and methods?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which PRINCE2 role has a specific responsibility for advising on the selection of the development strategy, design and methods?
A . Project Manager
B . Quality Assurance
C . Team Manager
D . Project Assurance

Answer: D