Which PRINCE2 role has a specific responsibility for identifying and advising the Project Manager of any issues and risks associated with a Work Package?

Which PRINCE2 role has a specific responsibility for identifying and advising the Project Manager of any issues and risks associated with a Work Package?
A . Senior Supplier
B . Team Manager
C . Project Support
D . Project Assurance

Answer: B