Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?

Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?
A . Project Manager
B . Project Support
C . Team Manager
D . Senior User

Answer: A