Which process could be used to increase compute resources to a virtual machine (VM) without first powering down?
A . Increase the CPU Share value on the V
C . vMotion the VM to an ESXi host with greater CPU capacity.
D . Add a vCPU to the VM using CPU hot add.
E . Move the VM into a Resource Pool with a larger CPU resource allocation.

Answer: D