Which process covers the activities of those at the level of management above the Project Manager?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which process covers the activities of those at the level of management above the Project Manager?
A . Controlling a Stage
B . Managing a Stage Boundary
C . Directing a Project
D . Managing Product Delivery

Answer: C